All tools

How we calculate

Every formula, conversion and default value used on NeatEstimate, in one place.

Unit conversions

FromToFactor
1 footmeters0.3048 (exact)
1 inchcentimeters2.54 (exact)
1 ft²m²0.09290304
1 yd³m³0.764555
1 ft³m³0.0283168
1 US ton (2,000 lb)metric tonnes0.90718474
1 lb/ft³kg/m³16.0185
1 acreft²43,560

We convert metric inputs to feet internally, calculate once and convert the results back, so both unit systems give the same answer.

Roof pitch

Pitch = rise ÷ run × 12. Angle = arctan(rise ÷ run).

The pitch multiplier is √(1 + (rise ÷ run)²). Rafter length = half the span (a full span for a shed roof) × multiplier. Roof area adds the eave overhang on every side.

Roofing

Roof area = (length + 2 × overhang) × (width + 2 × overhang) × pitch multiplier.

This works for gable, hip and shed roofs. One square is 100 ft². Bundles = squares × (1 + waste) × bundles per square, rounded up. Underlayment rolls cover 1,000 ft². Drip edge comes in 10 ft pieces. Ridge cap is figured at 33 linear ft per bundle.

Square footage

Rectangle = length × width.

Triangle = base × height ÷ 2. Circle = π × diameter² ÷ 4. Trapezoid = (top + bottom) ÷ 2 × height. Square yards = ft² ÷ 9. Acres = ft² ÷ 43,560.

Cubic yards

Cubic yards = length × width × depth (all in feet) ÷ 27.

Bag counts use 2 ft³ and 3 ft³ bags and are rounded up.

Gravel

Tons = cubic yards × density (tons per yd³).

Default densities are typical dry, loose values: gravel and crushed stone 1.4, pea gravel 1.35, river rock 1.3, crusher run 1.5, and sand 1.35 tons per yd³. Moisture and stone size change the real weight, so you can enter your supplier's figure.

Asphalt

Tons = area (ft²) × thickness (ft) × density (lb/ft³) ÷ 2,000.

The default density is 145 lb/ft³ for compacted hot-mix asphalt. Thickness means the compacted depth.

Deck material

Rows of boards = deck width ÷ (board width + gap), rounded up.

Linear feet = rows × deck length × (1 + waste). Boards = linear feet ÷ board length, rounded up. Joists = deck length ÷ spacing + 1. Screws = 2 per board at each joist, plus 5% spares, rounded up.

Rounding and waste

Material you buy in whole units (bundles, bags, boards, rolls) is always rounded up. Waste factors are added before rounding. You can set every waste factor to 0 to see the bare quantity.

How we test

Before a calculator is published we run its formulas against an independent implementation for hundreds of input combinations, including the defaults, the edge of each allowed range and metric inputs. We also check that switching units and back gives the same numbers. The results on each page should match a hand calculation using the formulas above.

Limits

Our calculators estimate quantities. They do not design structures, check spans or loads, or replace your local building code. See our disclaimer.

↑↓ move↵ openesc close